High Court considers the impact of loadshedding on fundamental constitutional human rights
At a glance
- Loadshedding in South Africa is causing human suffering and violating constitutionally protected rights.
- The Department of Public Enterprises plans to appeal a court ruling that found the state respondents responsible for the violation of rights due to loadshedding.
- The government has implemented an Energy Action Plan to increase generation capacity and explore alternative strategies, such as installing rooftop solar projects and expanding battery energy storage.
For anyone unfamiliar with the term, “loadshedding” refers to the ongoing rotational interruption to electricity supply in South Africa, which has been employed to safeguard the integrity of the national energy infrastructure (i.e. the grid) from a national blackout scenario where demand outweighs the supply. It is widely accepted by all (including Eskom in the matter at hand) that “loadshedding causes human suffering and has a detrimental impact on a variety of constitutionally protected rights”.
By Monday, 8 May 2023, the Department of Public Enterprises (Department) had issued a media statement announcing that the Minister would be lodging an urgent appeal to set aside the judgment. Apparently, the Department “has serious concerns about the implications of the court ruling on the current efforts to stabilise the national grid and get the country out of loadshedding”. Further, that the Department has “studied the ruling and has determined through legal advice that the prudent step to take is to lodge an appeal to set aside the ruling and allow for the ongoing efforts to end loadshedding to proceed without putting undue risk on the country’s grid infrastructure”.
Superior Courts Act
It appears that the Department’s legal strategy is to rely on the provisions of the Superior Courts Act 10 of 2013 that suspend the operation and execution of a decision which is the subject of an appeal. Scrutinising whether that would be successful is not the purpose of this note, rather, the purpose of mentioning these facts at the outset is to demonstrate that the judgment has caused quite a stir and prompted immediate action by the state respondents even before the implications of its application had been given an opportunity to be tested.
With that in mind, it is appropriate to turn to the judgment itself.
The application consisted of two parts: Part A and Part B. The High Court only heard Part A of the application and Part B of the application will be heard at a later date. The relief sought in Part A was to reduce the prejudicial impact of loadshedding on public health facilities, police stations and schools that do not have sufficient alternative energy sources available. The relief was premised on the assumption that Eskom, the Minister and the other state respondents have a constitutional and statutory obligation to provide electricity and that failure to do so violates fundamental constitutional rights, such as the right of access to healthcare services and the right to life.
Constitutional and statutory obligation
The High Court found that the state respondents do have a constitutional and statutory obligation to provide uninterrupted electricity to public health facilities, police stations and schools and that its conduct in implementing loadshedding amounted to a violation of the constitutional and statutory rights cited by the applicants. The High Court thus ordered the Minister, pending determination of Part B of the application, to take all reasonable steps within 60 days from the date of the order, whether in conjunction with other organs of state or not, to ensure that there is sufficient supply or generation of electricity to prevent any interruption of supply as a result of loadshedding to all public health facilities, public schools and police stations.
The court order does not prescribe how the Minister should provide uninterrupted power to these facilities but is crafted widely to provide the Minister with the discretion to decide how to deal with the power cuts at the relevant public institutions. However, the High Court held that the Minister must provide alternate sources of energy to maintain uninterrupted power in cases where it is difficult to isolate embedded structures/facilities to spare them from the effects of loadshedding.
Given the swift reaction by the Minister to appeal against the judgment, it is perhaps fruitless to consider the practical implications that it would or could have had, save to note that it could have unintended consequences like: (i) providing a basis for claims for common law damages or, alternatively, constitutional damages as a punitive measure; and (ii) cost implications on the fiscus, and so forth.
Nevertheless, while the nation awaits the outcome of this legal process it is useful to touch on other aspects relating to ongoing interventions to end loadshedding.
Energy Action Plan
In that regard, early in January 2023, the Government published an updated Energy Action Plan that sets out measures to be adopted by Government to steer the country away from the energy crises. Such measures include a roadmap for increasing the generation capacity between 2023 to beyond 2024. Furthermore, Government has continued to explore and investigate alternatives and strategies to navigate through the loadshedding such as turning public sector buildings into green buildings by installing rooftop solar projects. To account for the requirement for additional generation capacity, the Integrated Resource Plan (IRP) is being examined.
In accordance with section 35(4) of the Electricity Regulation Act 4 of 2006 read with regulation 4 of the Electricity Regulations on New Generation Capacity, the Minister developed the IRP, an electricity capacity plan, in consultation with the National Energy Regulator of South Africa. It outlines a framework for planning the expansion of generation capacity, interventions to control South Africa’s electricity demand from various sources of energy, and implementation timelines. The IRP is a “living plan” that must be periodically changed to account for and address the effects of shifting conditions affecting the supply and demand for electricity, but it has not been revised since 2019. On a positive note, the IPP office has recently issued a request for proposals for the battery energy storage to purchase 513 MW of capacity in the Northern Cape. The lack of grid capacity is anticipated to be somewhat alleviated by the new battery developments.
The information and material published on this website is provided for general purposes only and does not constitute legal advice. We make every effort to ensure that the content is updated regularly and to offer the most current and accurate information. Please consult one of our lawyers on any specific legal problem or matter. We accept no responsibility for any loss or damage, whether direct or consequential, which may arise from reliance on the information contained in these pages. Please refer to our full terms and conditions. Copyright © 2024 Cliffe Dekker Hofmeyr. All rights reserved. For permission to reproduce an article or publication, please contact us cliffedekkerhofmeyr@cdhlegal.com.
Subscribe
We support our clients’ strategic and operational needs by offering innovative, integrated and high quality thought leadership. To stay up to date on the latest legal developments that may potentially impact your business, subscribe to our alerts, seminar and webinar invitations.
Subscribe